The Flipflops Meltemi apartments are due to complete towards the end of June 2009. Here are the latest updates of the Flipflops development:
4th September 2009
Plastering is underway in
the social centre and all kitchen units are built in the apartments. We
are still waiting on work tops which we have been promised next week.
We have had a second delivery of tavertine to finsih certain areas around
the pool and the locks have been fitted to the front doors. 24th August 2009
The swimming pool has been grouted and the drainage grills in the edeges of the pool will now go in. The pillars around the pool area, shown on the photographs, cannot be rendered until the electirc wiring has been done and the electrician is working on this. We have been fined for working through the construction ban and so are having to keep noise to a minimum over the next few days. The ban ends on the 1st September and so it will be full steam ahead then and we will be able to concentrate on the social centre and tennis courts. 14th August 2009
12th August 2009
We are waiting on the next
delivery of doors and kitchens, this was due at the weekend so should
arrive any day now. 29th July 2009
The garden areas have moved
along substantially and the paths will soon go in. The pool is also closer
and the travertine surrounds are now on 24th July 2009
The travertine tiling has
begun on the pool and the photgraphs show the first few tiles being laid
at the pool edge 17th July 2009
Also on site the steps leading into the pool have been cast and the lights in the pool fitted. The pool is on track to be completed at the end of this month. Tomorrow the tiling will
start on the sunbathing area on top of the social centre. Landscaping
at the back of blocks A-D has begun and the soil for the grass areas has
been put down. The paths leading to the communal areas will follow. 14th July 2009
Glass panel inserts will
go in between the front spaces and work is moving through the blocks to
get these fitted. 8th July 2009
The summer has officially arrived in Bodrum and temperatures are rising, the view from the site is a stunning as ever and the balcony image shown here was taken from apartment A5. The second image is an aerial photo and it gives a good view of the site as a whole. The walls at the back of the site are completed and you can also make out the start of the social centre in the left hand corner. The pool has now had the final pour of concrete and people visitng the site have commented on just how large it is! The first image shows the communal steps at the back of the blocks. They have had the travertine tiling fitted and this tiling is continuing onto the communal areas and will form the paths and the sunbathing areas around the pool. The balcony railings will start to be fitted over the
next few days and this will take approximately a week to complete. 3rd April 2009 The marble window sills and marble wall copings have been fitted on D Block with the marble sills to be fitted around the edge of the roof. The dividing walls for the balconies are being erected (D block finished, C block and B Block underway). The internal tiling is also due to start once the isolation of the bathrooms and roof is finished for D block. This process will then move sequentially through each block. After tiling the windows and doors will be fitted (this being likely to be after the next update). Painting will follow accordingly. On the general site works, there has been some refinement of the retaining walls to the rear of blocks A to D and being continued around the sides of the blocks. The wall to the side of D block will be continued around in front of D and C blocks (forming the wall that is at the back of the pool). As soon as the wall gets built in front of D and C Blocks, the excavation of the pool and social areas will start, followed by the form work then the concreting of the structure.
11th March 2009
D Block was the first block to be started and is likely to be fully rendered and plastered in the next 2 weeks. Continuing work will move along from D Block across the other blocks subsequently. As the rendering finishes on each block, the marble window and door sills will be fitted followed by the windows and patio doors. All plumbing is finished & pressure tested and electrics are finished in blocks A to D and are now being completed in blocks E and F. Having been in a phase where there's little visual change for a couple of months due to the nature of the work going on, there will now be a lot of visible change in the next few weeks!
22nd January 2009
Work is on going at Flipflops. The steps at the back of the complex are complete and the second image has been taken from block A looking across to to block D. The electrical work is still on going on site and the plumbing works have begun. The next step will be the rendering which is due to start next month. The final photograph looks out over Gulluk Bay.
16th December 2008
It has been Bayram Holidays over in Turkey this last week and so there has been a break in work on site. The steps at the back of the complex are now almost complete and the electricians are back on site next week, after their recent holidays, to continue with the internal wiring. This will be the last update before Christmas however work is progressing as planned and further updates for the diary will be uploaded in January.
17th November 2008
All of the blocks are now at roof height and all internal walls are complete, apart from the first and top floor of F Block which will be finished this week. The first photograph shows the roof of F Block and the second looks down onto F & E Blocks. The internal wiring is underway and, as shown in the third photograph, the steps that run from the road down to the back of the units are being laid. The final image is the view from a B Block apartment. |
|
![]() |
|